New Requests for Electricity Service (Low Voltage)
Requesting to be provided with electricity services, the installation of new electricity service connections, and the installation of meters
Service Conditions
- Pay all the outstanding balance on the customer if any
Required Attachments
- Electricity supply application form
- Power condition requirements for building permits
- Building permit from the municipality
- Copy of the title deed
- Copy of the aerial map
- Copy of the survey certificate
- Copy of the address card
- Details of the required electrical power loads
- Confirmation of the power supply loads form from the main developer for private main projects
Legal Regulations
- Resolution No. 13 of 2006 related to the regulations of charges for the delivery of electricity and water services.
- Decree No. 2 of 2010 on the electrical wiring system
Fees
- Depends on the project : -
Process Time
- 45 Working Days
Service Provider
Electricity and Water Authority